| | #91 |
| Gear maniac Join Date: Jan 2007 Location: Vienna, Austria
Posts: 200
| week 7 there pics were taken the week before christmas: * plywood mounting frames for the doors in the main soundlock * some of the doors before mounting * installation of the door in mastering * main soundlock door (open) * edit room door (closed) |
| | |
| | #92 |
| Gear maniac Join Date: Jan 2007 Location: Vienna, Austria
Posts: 200
| week 7 - part II * entrance (no door) * entrance with door - this is a regular one, not a sound insulation door * bass traps and acoustic materials * more bass traps (different ones) * drywall buikders working on the ceiling in the lobby |
| | |
| | #93 |
| Gear maniac Join Date: Jan 2007 Location: Vienna, Austria
Posts: 200
| week 7 - part III * hardwood floor installation * hardwood floor finished * mastering room (a couple of hours before the hardwood floor went in) * delivery of our B&W N801 - we had to put them in the room as a christmas present to ourselves just to have a look, they are packed up again right now... ![]() * machine room I will add the pics of week 8 a little later in the evening ![]() |
| | |
| | #94 |
| Gear maniac Join Date: Jan 2007 Location: Vienna, Austria
Posts: 200
| christmas break |
| | |
| | #95 |
| Gear maniac Join Date: Jan 2007 Location: Vienna, Austria
Posts: 200
| week 8 cables: actually most of this was done by me and philipp during christmas break - a great guy and tech who works for us. * throughs (unfinished) * main soundlock - without computer floor * throughs (half finished) - this was done this week * cables on their way * into the machine room |
| | |
| | #96 |
| Gear maniac Join Date: Jan 2007 Location: Vienna, Austria
Posts: 200
| week 8 - part II * mastering room almost finished including HVAC diffusor (but still without any acoustic treatment) * mastering room ceiling hangers to support the wood ceiling * 5.1 control supply and return ducts and diffusors * iso wall - this is going to be a streched fabric wall. the entire cavity will be filled with sound attenuation blankets. you can see a bass trap which is going to dissapear behind this wall... * close up of the bass trap |
| | |
| | #97 |
| Gear maniac Join Date: Jan 2007 Location: Vienna, Austria
Posts: 200
| week 8 - part III * more cables * HVAC on the outside * machine room with installed ceiling * lobby * entrance |
| | |
| | #98 |
| Lives for gear | Great work. That floor is beautiful. And those doors look bulletproof. Great stuff... you must be thrilled! |
| | |
| | #99 |
| Gear maniac Join Date: Jan 2007 Location: Vienna, Austria
Posts: 200
| week 9 Thanks Stick - we're really happy the way the floor turned out. It actually looks even better in reality... ![]() Regarding the doors I would say bulletproof is underestimating their capabilities - we ordered them to withstand acoutic nightmares!! ![]() This week was the last week of construction (at least the dusty dirty part of it): Drywall builders left on Wednesday and HVAC was also finished this week. Some parts of the electric installation still needs to be finished - including final measurements of the CAT cables for the LAN. HVAC will go 'on air' next week after the electric instalation is finished. DSL modem, Wireless LAN and the FTP server have already been setup. The file server should arrive next week. We finally received our shipping from sterling modular, which took a lot longer than we thought because of all the terror paranoia - for some reason US authorities are also concerned when goods leave the country, don't ask me... Finally - as I'm writing this there should be some basic cleaning going on so from now on we should be clean. Still missing/to do's: * windows should get installed next week * the carpenter has to install and build the acoustic panels (he allready started this week) * some of the studio walls need a final layer of paint, some parts need laquer... * all sorts of patch bays and panels need to be soldered, furniture and equipement needs to be built, moved or installed. Here are some pics of last week: * 5.1 Control without acoustics * Entrance - almost done * HVAC ducts outside * Philipp installing the FTP Server * Sterling Modular shipping arrived!! |
| | |
| | #100 |
| Gear maniac Join Date: Jan 2007 Location: Vienna, Austria
Posts: 200
| Week 9 - Part II Sterling Modular Plan D ![]() |
| | |
| | #101 |
| Gear maniac Join Date: Jan 2007 Location: Vienna, Austria
Posts: 200
| week 9 - Part III * Helmholtz Mount for RPG Flutterfrees in 5.1 Control (behind surround speakers) * Helmholtz Mounts in Mastering; primary construction for acoustic ceiling (wood) * Iso 1 (wall to be covered with stretched fabric), hardwood floor (not oiled yet on this picture) * Restroom |
| | |
| | #102 |
| Gear maniac Join Date: Jan 2007 Location: Vienna, Austria
Posts: 200
| week 9 - Part IV * Reception view from entrance (no front desk yet) * Front desk - this was the last wall the drywall builders put up... * Bar / Client lounge almost finished |
| | |
| | #103 |
| Gear maniac Join Date: May 2007 Location: Baton Rouge, La
Posts: 253
| Simply put: WOW!! Thanks for sharing those photøs with us! They are amazing! I bet you're getting excited ... big time!! |
| | |
| | #104 |
| Gear addict Join Date: Nov 2004 Location: Switzerland-France
Posts: 374
| very interesting thread !! Good luck with everything Will let you know when I start mine.... |
| | |
| | #105 | ||
| Gear maniac Join Date: Jan 2007 Location: Vienna, Austria
Posts: 200
| Quote:
Quote:
Yes we are very excited about this, but for me personally the really exciting part is about to start - turning these very well isolated rooms into real studios... The last couple of days I've spent quite some time in the rooms installing the consoles and racks we received from sterling modular. Working on the consoles I got a first impression on how the rooms 'feel'. I have to say even without the acoustic treatment the rooms already have very controlled acoustics and I feel comfortable spending lots of time there - which I think is a pretty important aspect of a studio. ![]() Yesterday we received our shipping from RPG and today the carpenter will start installing tem, so we are definitely on our way of turning this place into a studio. ![]() I'll post some pics later when there is time... | ||
| | |
| | #106 |
| Lives for gear Join Date: May 2005 Location: Netherlands
Posts: 651
| Hi Mischa, looking good, I just remember putting the sterling-modular rack together ... one thing that annoys me is that the top ( inside ) of the 19 inch rack is not black ( I can see it in you're picture also ) .. but you look into the mdf .. even when fillling with a blank-pannel .. just last week I painted them black .. now it's okay ..... otherwise cool-place ..... enjoy ..... |
| | |
| | #107 |
| Gear nut Join Date: Jul 2006 Location: Switzerland
Posts: 103
| make me wanna move to Austria.... look fresh!! Good luck
__________________ http://www.dwellasound.com |
| | |
| | #108 |
| Gear Head | Coming along Beautifully!!! The rooms look like they are going to have a wonderful look and feel... |
| | |
| | #109 |
| Gear nut Join Date: Jan 2007 Location: NH
Posts: 139
| Everything looks fantastic! I am really enjoying this thread! -ScottyD |
| | |
| | #110 |
| Gear maniac Join Date: Jan 2007 Location: Vienna, Austria
Posts: 200
| week 10 Last week has been a little slower than the previous ones... Our electrician, the carpenter and the painter are the last workers to finish. The HVAC is comissioned and working - now it's nice and warm in the studio. Our order from RPG finally arrived on site, as have most of the materials for the room acoustics. I started bringing some of the packages with the Equipement that have arrived during the last weeks and we started unpacking and installing some of it. The pics: * Reception / client lounge close to finished * Shipping from RPG * Some wall panels * Wood ceiling in the mastering room |
| | |
| | #111 |
| Gear maniac Join Date: Jan 2007 Location: Vienna, Austria
Posts: 200
| week 10 - part II Mastering room pics: * Sterling Modular plan A * my temporary office (iMac on the side) * Absorbers covered with stretched fabric (not mounted yet) * Rear wall - 5 RPG Diffractals (not mounted yet) & 4 'Pawel' bass traps - the one in the left corner has its cardboard protection removed * B&W N801 moved (close) to their final position, Crane Song Avocet unpacked (remote on the console) |