Its almost 4am and time to stop. I could have got more done but I ran out of drywall. I broke two sheets, one when the drywall lift fell over.... extended to 13 ft.
it least it didn’t fall on me.
Quote:
| superburtm Is this the tracking room we are looking at? Or is it the whole facility? Looks like a great drum room!
|
Yep its the drum room
no ...... this is looking at what will be the control room and the tracking room with a large drum booth in the back.
control 27' X 23', studio 35' X 23' with 13ft ceiling. and offices and break room in front. (behind where I am standing taking these pics)
Quote:
GPl 42 sheets...man my arms are hurting just reading this
Are you doing this yourself? Of course you would need help with the drywall, but I mean are you doing the construction?
|
So far I have done all the work myself but the drywall lift makes life easy.
Saturday I will have 2 pallets of rock delivered 96 sheets, and 90 2x4x16s for my side walls. all this work is for soundproofing and is not very glamorous.
3 of the side walls are 8" concrete and dont require much soundproofing, the one side wall is just a sheetrock partition wall with a business on the other side.
All the soundproof walls will be double 12" wall construction with 3 layers of 5/8" sheetrock. im getting tired just thinking about it.
After reading Dangerous Dave’s thread it makes me wish I had a contractor working for me ,..... naaa

I couldn’t afford that and some day this will all be done and there will be music blasting in here instead of hammers pounding!
more pics. as I make Progress
steve