| A pallet of blocks arrived this week... A pallet of blocks has been delivered so that the masons can build a practice wall and verify that the dimensions of the blocks are within spec. With 27 blocks laid end-to-end on the long side of the music room and 36 blocks laid end-to-end on the long side of the garage, we're verifying that the blocks are consistent in size and that fabrication errors won't add up to a building that won't stand up.
No photos of the pallet or the porta-potty, but ground breaking will begin next week.
Happy new year to all! |