| Hi everyone,
Right now everything is moving pretty fast... Last week the walls of the floating construction went up. But the really interesting part (for me) was the ceiling. Again I included lots of pictures (apologies to Jules - I hope it is OK to post this many).
HVAC fitters were busy putting in lots of ducts - In the place that is going to be the sound locks you can hardly see the raw ceiling any more.
Electric installation should finally start next week - there simply was not enough room for them to start last week so it had to be postponed...
These pictures show the spring ceiling hangers mounted on the primary suspended ceiling construction that was welded to the existng ceiling last week. They are very low profile, this way not much hight is lost. |